PMI Agile Certification Practitioner(PMI ACP) Exam Practice Test 1
© examsiri.com
Question : 36 of 40
Marks:
+1,
-0
As your agile team leader, Jaya has been tracking the iteration velocity and has compared it to the time remaining on the project. Jaya concludes that the fewest number of iterations that can be completed per month is seven, and the most
possible is ten. What is this measurement called?