PMI Agile Certification Practitioner(PMI ACP) Exam Practice Test 1

© examsiri.com
Question : 20 of 40
 
Marks: +1, -0
As the project manager for his agile team at Morgan Manufacturing, Alex is coordinating a workshop. He has asked the team to visualize how their release will go in a couple of months after a little bit of time has passed after the release. Alex’s team must list everything that was delivered and also describe how the release went. What is this activity called?