PMI Agile Certification Practitioner(PMI ACP) Exam Model Test 8

© examsiri.com
Question : 33 of 43
 
Marks: +1, -0
There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story.
Who should the Scrum Master invite to the meeting?