Question : 19 of 43
Marks:
+1,
-0
Two teams have received project requirements and completed estimates. Team A estimates 420 story points for scope and 30 story points for velocity per sprint. Team B estimates 280 story points for scope and 20 story points for velocity per sprint. Both teams have same number of team members and have an assumed sprint duration of 2 weeks.
What can an agile practitioner conclude about team A and team B's estimates?
What can an agile practitioner conclude about team A and team B's estimates?