PMI Agile Certification Practitioner(PMI ACP) Exam Model Test 7

© examsiri.com
Question : 4 of 50
 
Marks: +1, -0
Midway through a sprint, the scrum master identifies that reassigning a certain task could help the team meet its sprint goals.
What should the scrum master do next?