Question : 31 of 50
 
Marks: +1, -0
A product owner for two highly visible projects spends a great deal of time meeting with and reporting to senior stakeholders. The product owner is overwhelmed because both project teams request clarification on the requirements and the overall priorities.
What should the agile project manager do?