PMI Agile Certification Practitioner(PMI ACP) Exam Model Test 4

© examsiri.com
Question : 29 of 50
 
Marks: +1, -0
Based on the following information, determine the number weeks until the next release.
Length of a Sprint =2 weeks
Velocity of team =35 points
Number of story points assigned to minimum marketa ble features (MME)=280 points
Go to Question: