Suppose your team velocity is 8 story points, and the product backlog items are ordered by priority as shown below. If you are in a Sprint Planning meeting and need to commit to the User Stories for the next iteration, which ones will you select?
Story 1=3 Story Points
Story 2 =4 Story Points
Story 3=3 Story Points
Story 4 = 1 Story Points
Story 1=3 Story Points
Story 2 =4 Story Points
Story 3=3 Story Points
Story 4 = 1 Story Points