PMI Agile Certification Practitioner(PMI ACP) Exam Model Test 3

© examsiri.com
Question : 29 of 50
 
Marks: +1, -0
Suppose 8 new members joined the development team, and the team size is now 15. The daily Scrum is getting noisy and exceeding the 15 minutes time-box. What is the most effective way to address this situation?