NIFT UG 2010 Question Paper with solutions

© examsiri.com
Question : 136 of 149
 
Marks: +1, -0
A contractor agreeing to finish a work in 150 days employed 75 men, each working for 8 h daily. After 90 days only 27 of the work was completed. How many more men would be put on now, each working 10 h daily so as to finish the work in the stipulated time?
Go to Question: