Question : 99 of 200
 
Marks: +1, -0
Two coal loading machines, each working 12 h per day for 8 days, handle 9000 tonne of coal with an efficiency of 90%, while 3 other coal loading machines at an efficiency of 80% are set to handle 12000 tonne of coal in 6 days. How many hours per day should each machine work?