Madhya Pradesh Police Exam Model Paper 9

© examsiri.com
Question : 69 of 100
 
Marks: +1, -0
If 12 men complete one-fourth of a piece of work in 10 days, working 8 hours a day, in how many days 15 men complete full piece of work when they work 6 hours a day?