Question : 18 of 54
 
Marks: +1, -0
A small manufacturing firm produces two types of gadgets A and B. which are first processed in the foundary, and then sent to another machine for finishing. The number of man-hours of labour required in each shop for the production of each unit of A and B, and the number of man-hours for the firm available per week are as follows :
FoundaryMachines - Shop
Gadget A105
Gadget B64
Firms capacity per
Week in man hours
1000600
Let the firm manufacture x units of A and y units of B. The constraints are: