IBPS RRB Office Assistant 23 Sep 2017 Paper
© examsiri.com
Question : 43 of 80
Marks:
+1,
-0
Working together, A and B can complete a given task in 7
days. Working alone, A and C take 12 days and 30 days respectively to complete the same task. In how many days can B and C working together, complete the same task ?
Go to Question: