Question : 24 of 100
 
Marks: +1, -0
A group of men were assigned a work. After half of the work completed, double the number of men joined the original group. Now the work gets completed 6 days earlier than the scheduled number of days. What is the total number of days the initial group of men would have taken to complete the work?