IBPS Clerk Prelims 2013 Paper
© examsiri.com
Question : 119 of 200
Marks:
+1,
-0
56 workers can finish a piece of work in 14 days. If the work is to be completed in 8 days, then how many extra workers are required?
Go to Question: