IBPS Clerk Mains 2018 Paper
© examsiri.com
Question : 79 of 190
Marks:
+1,
-0
4 men & 18 women can do a piece of work in 2.5 days, then in how many days 12 women can complete the same piece of work?
A. Ratio of efficiency of men to women is 3 : 2.
B. 6 men & 6 women can complete the same work in 4 days.
A. Ratio of efficiency of men to women is 3 : 2.
B. 6 men & 6 women can complete the same work in 4 days.
Go to Question: