Question : 13 of 200
 
Marks: +1, -0
Find the number of days in which Q can do a job if P can do the same job in 8 days.
A. Q is 60% more efficient than P.
B. P and Q together can do the job in 3
1
13
days.
C. P is 37
1
2
% less efficient than Q.