GATE Mechanical Engineering (ME) 2021 Shift 1 Solved Paper

© examsiri.com
Question : 38 of 65
 
Marks: +1, -0
A set of jobs A, B, C, D, E, F, G, H arrive at time t = 0 for processing on turning and grinding machines. Each job needs to be processed in sequence - first on the turning machine and second on the grinding machine, and the grinding must occur immediately after turning. The processing times of the jobs are given below.
Job
A
B
C
D
E
F
G
H
Turning (minutes)
2
4
8
9
7
6
5
10
 Grinding (minutes) 
6
1
3
7
9
5
2
4

If the makespan is to be minimized, then the optimal sequence in which these jobs must be processed on the turning and grinding machines is
Go to Question: