GATE Mechanical Engineering (ME) 2020 Shift 2 Solved Paper
© examsiri.com
Question : 8 of 65
Marks:
+1,
-0
It was estimated that 52 men can complete a strip in a newly constructed highway connecting cities P and Q in 10 days. Due to an emergency, 12 men were sent to another project. How many number of days, more than the original estimate, will be required to complete the strip?
Go to Question: