GATE Mechanical Engineering (ME) 2020 Shift 2 Solved Paper
© examsiri.com
Question : 16 of 65
Marks:
+1,
-0
Consider the following network of activities, with each activity named A-L, illustrated in the nodes of the network.
The number of hours required for each activity is shown alongside the nodes. The slack on the activity L, is ______ hours.
- Your Answer:
Go to Question: