Question : 59 of 65
 
Marks: +1, -0
A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
ActivityImmediate
predecessor
Estimated
duration (weeks)
P-5
Q-1
RQ2
SP,R4
TP6
US,T3
If all activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is ___________