GATE Mechanical Engineering (ME) 2017 Shift 2 Solved Paper
© examsiri.com
Question : 59 of 65
Marks:
+1,
-0
A project starts with activity A and ends with activity F. The precedence relation and durations of the activities are as per the following table:
The minimum project completion time (in days) is ________.
|
Activity |
Immediate predecessor |
Duration (days) |
|
A |
- |
4 |
|
B |
A |
3 |
|
C |
A |
7 |
|
D |
B |
14 |
|
E |
C |
4 |
|
F |
D, E |
9 |
The minimum project completion time (in days) is ________.
- Your Answer:
Go to Question: