GATE Mechanical Engineering (ME) 2016 Shift 2 Solved Paper
© examsiri.com
Question : 65 of 65
Marks:
+1,
-0
A project consists of 14 activities, A to N. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node 10 is _______
- Your Answer:
Go to Question: