GATE Mechanical Engineering (ME) 2016 Shift 1 Solved Paper

© examsiri.com
Question : 10 of 65
 
Marks: +1, -0
P, Q, R and S are working on a project. Q can finish the task in 25 days, working alone for 12 hours a day. R can finish the task in 50 days, working alone for 12 hours per day. Q worked 12 hours a day but took sick leave in the beginning for two days. R worked 18 hours a day on all days. What is the ratio of work done by Q and R after 7 days from the start of the project?
Go to Question: