Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project
Activity
Duration (days)
1-2
2
2-3
1
4-3
3
1-4
3
2-5
3
3-5
2
4-5
4

The critical path (CP) in the network is