Question Numbers: 62-63
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
Activity Predecessors Duration (days)
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
Activity Predecessors Duration (days)
|
Activity |
Predecessors |
Duration(days) |
|
A |
- |
3 |
|
B |
A |
4 |
|
C |
A |
5 |
|
D |
A |
4 |
|
E |
B |
2 |
|
F |
D |
9 |
|
G |
C, E |
6 |
|
H |
F, G |
2 |
© examsiri.com
Question : 63 of 65
Marks:
+1,
-0
If the duration of activity f alone is changed from 9 to 10 days, then the