The overcurrent relays for the line protection and loads connected at the buses are shown in the figure.
The relays are IDMT in nature having the characteristic
The maximum and minimum fault currents at bus B are 2000 A and 500 A respectively. Assuming the time multiplier setting and plug setting for relay RB to be 0.1 and 5A respectively, the operating time of RB (in seconds) is_______
The relays are IDMT in nature having the characteristic
The maximum and minimum fault currents at bus B are 2000 A and 500 A respectively. Assuming the time multiplier setting and plug setting for relay RB to be 0.1 and 5A respectively, the operating time of RB (in seconds) is_______