Question : 15 of 65
 
Marks: +1, -0
A company needs to develop a strategy for software product development for which it has a choice of two programming languages L1 and L2. The number of lines of code (LOC) developed using L2 is estimated to be twice the LOC developed with L1. The product will have to be maintained for five years. Various parameters for the company are given in the table below. 
Parameter
Language L1
Language L2
 Man years needed for development
LOC/10000
LOC/10000
 Development cost per man year
Rs. 10,00,000
Rs. 7,50,000
 Maintenance time
5 years
5 years
 Cost of maintenance per year
Rs. 1,00,000
Rs. 50,000

Total cost of the project includes cost of development and maintenance. What is the LOC for L1 for which the cost of the project using L1 is equal to the cost of the project using L2?  