The activities of a project are given in the following table along with their durations and dependency.
​The total float of the activity E (in days) is ________. (in integer)
| Activites | Duration (days) | Depends on |
| A | 10 | - |
| B | 12 | - |
| C | 5 | A |
| D | 14 | B |
| E | 10 | B, C |
​The total float of the activity E (in days) is ________. (in integer)