Question : 52 of 65
 
Marks: +1, -0
The activity details for a small project are given in the Table.
 Activity 
Duration (days)
Depends on
A
6
-
B
10
A
C
14
A
D
8
B
E
12
C
F
8
C
G
16
D, E
H
8
F, G
K
2
B
L
5
G, K

The total time (in days, in integer) for project completion is ______ 