Question : 39 of 65
 
Marks: +1, -0
The network of a small construction project awarded to a contractor is shown in the following figure. The normal duration, crash duration, normal cost, and crash cost of all the activities are shown in the table. The indirect cost incurred by the contractor is INR 5000 per day.
ActivityNormal Duration (days)Crash Duration (days)Normal Cost
(NR)
Crash Cost (INR)
P641500025000
Q52600012000
R5380009500
S63700010000
T3260009000
U2140006000
V422000028000
If the project is targeted for completion in 16 days, the total cost (in INR) to be incurred by the contractor would be