Question : 48 of 65
Marks:
+1,
-0
The ultimate a wastewater sample is estimated as of COD. The COD of this wastewater is . Considering first order BOD reaction rate constant (use natural per day and temperature coefficient , the BOD value (in , up to one decimal place) after three days of incubation at for the wastewater will be __________