A city generates 40×106kg of municipal solid waste (MSW) per year, out of which only 10% is recovered\/recycled and the rest goes to landfill. The landfill has a single lift of 3m height and is compacted to a density of 550kg/m3. If 80% of the Iand fill is assumed to be MSW, the landfill area (in m2, up to one decimal place) required would be