GATE Civil Engineering (CE) 2017 Shift 2 Solved Paper
© examsiri.com
Question : 31 of 65
Marks:
+1,
-0
A sheet pile has an embedment depth of 12 m in a homogeneous soil stratum. The coefficient of permeability of soils is 10 –6 m/s. Difference in the water levels between the two sides of the sheet pile is 4m. The flow net is constructed with five number of flow lines and eleven number of equipotential lines. The quantity of seepage (in cm3/s per m. up to one decimal place) under the sheet piles ________
- Your Answer:
Go to Question: