GATE Civil Engineering (CE) 2017 Shift 2 Solved Paper

© examsiri.com
Question : 28 of 65
 
Marks: +1, -0
For a construction project the mean and standard deviation of the completion time are 200 days and 6.1 days respectively. Assume normal distribution and use the value of standard normal deviate z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be ________
  • Your Answer: