The activity details of a project are given below:
Activity
Depends on
Duration (in days)
P
Q
R
S
T
U
V
-
P
Q, T
R
P
Q, T
U
6
15
12
16
10
14
16

The estimated minimum time (in days) for the completion of the project will be_______ 