The ordinates of a 2-hour unit hydrograph for a catchment are given as
Time (h) 0 1 2 3 4
Ordinate (m3/s) 0 5 12 25 41
The ordinate (in m3/s) of a 4-hour unit hydrograph for this catchment at the time of 3 h would be ________
Time (h) 0 1 2 3 4
Ordinate (m3/s) 0 5 12 25 41
The ordinate (in m3/s) of a 4-hour unit hydrograph for this catchment at the time of 3 h would be ________