GATE Civil Engineering (CE) 2016 Shift 2 Solved Paper

© examsiri.com
Question : 20 of 65
 
Marks: +1, -0
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.
Activity
Duration
(days)
Activity
Duration (days)
A
Inauguration
1
G
Flooring
25
B
Foundation work
7
H
Electrification
7
C
Structural construction - 1
30
I
Plumbing
7
D
Structural construction - 2
30
J
Woodwork
7
E
Brick masonry work
25
K
Coloring
3
F
Plastering
7
L
Handing over function
1
 

Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively:
Go to Question: