GATE Civil Engineering (CE) 2016 Shift 2 Solved Paper
© examsiri.com
Question : 20 of 65
Marks:
+1,
-0
A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below.
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively:
|
Activity |
Duration (days) |
Activity |
Duration (days) |
||
|
A |
Inauguration |
1 |
G |
Flooring |
25 |
|
B |
Foundation work |
7 |
H |
Electrification |
7 |
|
C |
Structural construction - 1 |
30 |
I |
Plumbing |
7 |
|
D |
Structural construction - 2 |
30 |
J |
Woodwork |
7 |
|
E |
Brick masonry work |
25 |
K |
Coloring |
3 |
|
F |
Plastering |
7 |
L |
Handing over function |
1 |
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively: