GATE Civil Engineering (CE) 2016 Shift 1 Solved Paper
© examsiri.com
Question : 49 of 65
Marks:
+1,
-0
The Optimistic Time (O), Most likely Time (M) and Pessimistic Time (P) (in days) of the activities in the critical path are given below in the format O-M-P.
The expected completion time (in days) of the project is _________
The expected completion time (in days) of the project is _________
- Your Answer:
Go to Question: