The 4-hr unit hydrograph for a catchment is given in the table below. What would be the maximum ordinate of the S-curve (in m3/s) derived from this hydrograph?
|
Time (hr) |
0 |
2 |
4 |
6 |
8 |
10 |
12 |
14 |
16 |
18 |
20 |
22 |
24 |
|
Unit hydrograph Ordinate (m3/s) |
0 |
0.6 |
3.1 |
10 |
13 |
9 |
5 |
2 |
0.7 |
0.3 |
0.2 |
0.1 |
0 |