Workability of concrete can be measured using slump, compaction factor and Vee-bee time. Consider the following statements for workability of concrete:
(i) As the slump increases, the Vee-bee time increases.
(ii) As the slump increases, the compaction factor increases.
Which of the following is TRUE?
(i) As the slump increases, the Vee-bee time increases.
(ii) As the slump increases, the compaction factor increases.