Given: 20 builders can excavate a building in 50 days. Formula used: (M1 × D1)/W1 = (M2 × D2)/W2, where M = Number of workers, D = Number of days and W = work Calculation: Let total work be 50unitsEfficiency of 20 builders = 50/50 = 1 units/day After 10 days, 20 more builders join them, that is 40 builders work after 10 days Work left after 10 days = 50 - 10 = 40 units Let the required number of days be D
⇒ ⇒ days Alternate Method Let 1 builder do 1 unit/day work. Hence, total work = units Work done by 20 builders in 10 days = 20 × 10 = 200 units Now, remaining work = units ∴ Required time = days.