Question : 22 of 30
 
Marks: +1, -0
A company uses its own private cloud, which has few available resources. Mission-critical systems and other information systems are running on it. A new system will be deployed on the private cloud. The following tests are included in the test plan:
● Load test (2h)
● Backup/restore test (6h)
● Functional test (8h)
● Failover test (1h)
The work schedule of the existing system is shown below.
   System open  System close  Batch job
 ERP (mission critical)  9:00  22:00  22:00-00:00
 Groupware  24h active  no batch
 Internal web  24h active  06:00-08:00
 Official website  24h active  00:00-00:30
To minimize the effect to the existing system, which of the following schedules is MOST suitable for the load test?