Chain Rule Practice Test 3 with solutions
© examsiri.com
Question : 8 of 10
Marks:
+1,
-0
400 persons, working 9 hours a day complete th of the work in 10 days. The number of additional persons, working 8 hours a day, required to complete the remaining work in 20 days, is:
Go to Question: