Chain Rule Practice Test 1 with solutions
© examsiri.com
Question : 25 of 40
Marks:
+1,
-0
A piece of work can be done by 34 workers in
15 days. How long will 51 workers take in
order to do the same work?
15 days. How long will 51 workers take in
order to do the same work?