Question : 19 of 100
Marks:
+1,
-0
A contractor undertook to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional man, how many days behind schedule would it be finished ?