CDS Model Paper 4 Mathematics

© examsiri.com
Question : 13 of 100
 
Marks: +1, -0
24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is: