CDS Model Paper 1 Mathematics
© examsiri.com
Question : 14 of 100
Marks:
+1,
-0
A and B together can do a piece of work in 12 days and B and C finish the same work together in 16 days. After A has worked on it for 5 days and B for 7 days, C finishes it in 13 days. In how many days will C alone be able to finish the work?