CAPM Certification Practice Test 9
© examsiri.com
Question : 45 of 50
Marks:
+1,
-0
Leon is the project manager of the GHA Project for his company. A recent earned value management calculation shows that Leon has a CPI of .98 on this project. A project that has a CPI of .98 means what?
Go to Question: